In both office and industrial leasing, there can be a substantial gap between the Tenant Installation (TI) allowance offered by a landlord and the cost of creating a space that actually works for the occupier. It is a gap that deserves attention before a tenant commits to a lease.
Industrial premises: the old rule of thumb
Industrial lease negotiations have often referred to a TI contribution equivalent to roughly one month of rental for each year of the lease, usually calculated on the office component. That convention may leave a tenant with significant additional expenditure for partitioning, power, lighting, air-conditioning, data cabling and joinery. The precise allowance and scope always depend on the negotiated deal.
Office premises: allowances versus actual costs
Illustrative allowance levels discussed in the market — such as R400–R600/m² for some A-grade offices and around R1,000/m² for certain higher-grade buildings — can be materially below the cost of a tenant-specific installation. Depending on specifications and building condition, even a relatively straightforward white-box fit-out may be significantly more expensive.
These are discussion benchmarks, not universal market rates or current quotations. Each property needs an itemised scope and an updated contractor estimate.
A simple 200 m² illustration
- Illustrative fit-out cost
- R420,000
- Illustrative landlord TI allowance
- R100,000
- Potential tenant shortfall
- R320,000
This simplified example excludes other possible relocation, professional, IT, furniture and financing costs. It is not a quote for a specific premises.
What should be negotiated upfront?
- An agreed schedule of finishes and a clear split between landlord and tenant works.
- A realistic TI allowance based on an itemised, current fit-out budget.
- Where appropriate, a rent-free installation period or an alternative financial incentive.
- Partial or full turnkey delivery by the landlord, with responsibility for overruns clarified.
- Reinstatement and white-boxing obligations at lease expiry, not just move-in costs.
There is a direct link between this issue and the meaning of Grey Box, White Box and Turnkey. Unless both parties agree on exactly what will be delivered, a seemingly generous allowance can still produce an unwelcome surprise.
It is also why newer approaches such as Redefine's Swift Space are worth examining: reducing the installation burden can be as important as increasing the headline allowance.
The real negotiation is about the total cost of occupation — and who funds the work needed to make the premises usable.
For tenants, landlords and brokers alike, transparency on these costs early in the process can prevent difficult negotiations and avoidable disappointment later on.